ITB #2505 Yamhill Valley Campus (YVC) Building 2 Tenant Improvement
Last Updated: 5/8/2025 3:36 PMThe project comprises a 31,636 SF of new office building space for the Health and Human Services department.
Notice TypeOrdinary Construction
Bid Closing Date & Time6/5/2025 1:00 PM
Pre-bid Meeting (Mandatory)5/15/2025 10:00 AM
Work Start Date7/1/25
Substantial Completion Date5/1/26
Final Completion Date6/1/26
Project Estimate$5,000,000
The building will remain occupied and the portion of the space that is not under construction will remain fully operational. The Work shall be phased in two timeframes, as shown on the Drawings:
Phase I Final Completion: December 1, 2025
Phase II Final Completion: June 1, 2026.